Bergen County/Essex County

Kingsland Avenue (Avondale and De Jessa Memorial) Bridge over the Passaic River

Township of Lyndhurst and Township of Nutley, New Jersey

Bergen County/Essex County

Kingsland Avenue (Avondale and De Jessa Memorial) Bridge over the Passaic River

Township of Lyndhurst and Township of Nutley, New Jersey

Environmental Resources

Bergen County and Essex County have joint jurisdiction of the Clay Street Bridge, however the bridge replacement is being federally funded. Any transportation projects receiving federal funding follow the National Environmental Policy Act (NEPA) process.

The New Jersey Department of Transportation (NJDOT) Bureau of Environmental Resources (BEPR) oversees this aspect of the project in cooperation with both Counties and NJTPA. They coordinate with the permitting agencies, such as NJDEP and NJSHPO (New Jersey State Historic Preservation Office), to develop a cohesive plan for proposed improvements. The agencies look carefully at comments from the public; therefore, community involvement is an important part of the environmental process and moving the project forward with consensus and environmental compliance.

The LCD Study Phase required the identification of any environmental concerns and to develop an environmental profile. When analyzing alternatives, the Project Team looked to avoid or minimize environmental impacts and, if that was not possible, then to provide mitigation. The environmental resources include air, noise, hazardous or contaminated sites, parks, wetlands, water resources, social and economic impacts, and cultural resources such as historic structures and facilities.

During the LPE Phase environmental and cultural resource studies will continue. The results of the environmental screening and cultural resource studies, which are part of the project schedule, are presented at the public meetings.

Environmental mitigation and permitting are part of the FD Phase.

The NJDOT Bureau of Environmental Program Resources oversees compliance with the principles or essential elements of NEPA compliance throughout the project delivery process, including:

  • Assessment of the social, economic, and environmental impacts of a proposed action or project
  • Analysis of a range of reasonable alternatives to the proposed project, based on the applicants defined purpose and need for the project
  • Consideration of appropriate impact mitigation: avoidance, minimization and compensation
  • Inter-agency participation: coordination and consultation
  • Public involvement including opportunities to participate and comment
  • Documentation and disclosure

Project Development Phases

Documentation/Action

Coordination

Concept Development

Purpose & Need, Environmental Screening Report and Alternatives Analysis

Project Team, Public, Stakeholders and Permitting Agencies

Preliminary Engineering

Technical Environmental Studies (as needed), Categorical Exclusion

Project Team, Public, Stakeholders, Permitting Agencies

Final Design

Permits, Environmental Reevaluation, Environmental Plan Sheets and Environmental Mitigation

Project Team, Public, Stakeholders, Permitting Agencies

Construction

Environmental Mitigation, Construction Monitoring

Project Team, Public, Stakeholders, Permitting Agencies, Contractor

Environmental Documents:

Local Capital Project Delivery Process

Purpose & Need Statement

Data Collection & Environmental Screening Report

Selection of Preliminary Preferred Alternative

Concept Development Report

NEPA Classification

Create Design Communications Report

Initial Public Outreach & Involvement

Approved Design Exception Report

Cost Estimates (Final Design, ROW & Construction)

Approved Environmental Document

Approved Project Plan

Preliminary Engineering Report

Update Design Communications Report

Continued Public Outreach & Involvement

Construction Contract Documents & PS&E Package

Environmental Reevaluations

Environmental Permits

Acquisition of ROW

Update Design Communications Report

Continued Public Outreach & Involvement

Implement and Complete Construction

Continue Public Outreach

As-Builts

Update and Finalize Design Communications Report

Close-out Documentation

Recent News

  • Update: May 23, 2024

    Meeting Report for Public Information Center (PIC) Meeting No. 1 is now available

  • Update: February 29, 2024

    Thank you to those who were able to attend the Public Information Center (PIC) Meeting No. 1 for the Local Preliminary Engineering (LPE) phase.

Translate »